Centerville Railroad Safety Improvements

Overview

The Centerville Railroad Corridor Quiet Zone Project proposes to install safety improvements at six at-grade railroad crossings and to eliminate the current federal requirement for railroad horn blasts. The project is being implemented in coordination with Union Pacific Railroad (UPRR), the California Public Utilities Commission (CPUC), the Federal Railroad Administration (FRA), and the Altamont Commute Express (ACE). The street crossings included in the project include: Blacow Road, Dusterberry Way, Maple Avenue, Fremont Boulevard, Shinn Street, and Clarke Drive.

 Centerville Railroad Safety Improvement Project_October 2023

Objectives

The Centerville Railroad Safety Improvement Project seeks to achieve the following goals:

  • Implement supplemental safety measures (SSMs) at each at-grade crossing to improve the safety for all modes of travel across the railroad tracks.
  • Seek funding from regional transportation sources (County, State and Federal) to implement railroad crossing safety improvements. The project has been identified as a priority for implementation by 2030 as part of the County Transportation Plan (CTP) for Alameda County.
  • Establish a quiet zone in the Centerville neighborhood and along the ACE Train corridor within Fremont.

Status

The City of Fremont is funding planning efforts to facilitate the project. On December 14, 2021, the Fremont City Council approved a “notice of intent” to create a railroad quiet zone along the Centerville corridor. The City has hired RailPros to assist with preliminary concept development and agency coordination for safety enhancements.

Schedule

 action item  date/duration  initiated by
 Diagnostic Meeting
  • Pre-Diagnostic Meetings
  • Diagnostic Meeting
  • Approval of Diagnostic Meeting Minutes
 
  • Held February 7, 2023 & March 30, 2023
  • Completed May 10, 2023
  • Completed October 20, 2023
 City of Fremont
  Approval of Preemption Timing   Q4 2024   City of Fremont 
 Application to CPUC for Railroad Crossing Modification   Q1 2025  City of Fremont 
 Submit Notice of Intent
 Q1 2025 City of Fremont
 CPUC Permit Approval   Q1 2025  CPUC 
 Completion of Construction Plans for Safety Project including Approval of Plans by UPRR   TBD  City of Fremont 
 Signal and Track Design by UPRR   TBD  UPRR
 Construction & Maintenance Agreement between City and UPRR  TBD  UPRR
 Bid and Award of City Construction Contract   TBD  City of Fremont
 City Project Construction Period  TBD  City of Fremont
 UPRR Project Construction Period   TBD  UPRR
 Quiet Zone Community Education Process   TBD  City of Fremont
 Submit Notice of Establishment  TBD  City of Fremont
 Establish Quiet Zone  TBD  City of Fremont

Cost

 Concept Planning  $230,000
 Preliminary Design/Environmental Review  $500,000
 Final Design  TBD
 Construction  TBD

 Funding 

 City of Fremont  $730,000
 Final Design  TBD
 Construction  TBD

Additional Documents

Contact

Jeanne Suyeishi
Principal Civil Engineer
510-494-4728
Email

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Download Acrobat Reader Windows Media Player Download Windows Media Player Word Viewer Download Word Viewer Excel Viewer Download Excel Viewer PowerPoint Viewer Download PowerPoint Viewer