About the Project
The scope of work for this project will include the demolition and removal of the existing basketball court with basketball standard and installation of a two new back-to-back half size courts with basketball standards near Seneca Park Loop. Work will also include the installation of concrete paving to the new courts from the existing sidewalk, minor grading with relocation of on-site soil, new sod installation with modifications to the existing irrigation system and off-haul of excess excavated soils.
Timeline
The project opened bids on January 6th, 2023. Construction is slated to begin in April 2023 and is expected to be completed by August 2023.